Storehouses for paper, printing-house and office building, city of Sofia Back

Employer: SP Impera – Ivan Ivanov

Designer: Gravity EOOD, city of Sofia

Location: City of Sofia, Rozhen Blvd.

Term under the Contract: 9 months

Term of execution: 9 months

Budget: In conformity with agreed financial parameters

Excess over the budget: None

Distribution: Industrial part at two levels and an office part at three levels.

Floor built-up area: 1639,65 m²

Vertical leveling: Asphalt pavement of roads and a parking lot, sidewalks and curbs.

Description of the activities: Rough construction – Excavation – embankment works, reinforcement, concrete, shuttering works were executed, masonries and insulations were made.

Architectural-construction works – pavement with ground concrete and bastard granite, gypsum plaster as well as painting with latex on walls and ceilings, noise insulating activities.

Focus: Industrial enterprise with enhanced requirements for fire protection.

Execution: Excellent quality without any remarks.

Status of the Project: Functioning, Written Statement of Ascertainment for the establishment of the appropriateness of the construction for occupation of 08.12.2010.